Sewer works in your area from October 2022

 

You might not notice a lot of the work we do because most of it is beneath your feet. Every day, we’re maintaining and upgrading the pipes and pumps that keep the sewage network flowing.

With some upcoming works in Higgins Rd, Wood St, Hobart St and London St, Bentleigh you might see us or our contractor ZJW (Zinfra, Jaydo, WSP, Joint Venture) around. Here’s what to expect while we get the job done.

What we're doing

The project will increase the capacity of the sewer network to cater for population growth in the area and future proof the sewerage system.

You shouldn’t notice any change to your water or sewer services while we work.

When it's happening

We’ll commence investigative works and construction from mid October 2022 until early 2024 (weather permitting).

You can expect us to work Monday to Friday between 7 am and 5 pm and on Saturday between 8 am and 3.30 pm. On the odd occasion, we might need to work at other times for safety, technical or permit reasons.

Due to technical reasons, we'll need to undertake remediation works on Higgins Road, between Jasper Road and Wood Street, from 12 March until early April 2024 (weather permitting).  

We're also returning to undertake works at London Street between Hobart and Auckland Streets from 4 April until 10 April 2024. The area will be open to local traffic only during this time.

We've encountered delays due to technical reasons and project completion is now anticipated for early 2024.

What might impact you

We’ll do our best to keep impacts to a minimum, however these are the kinds of things you might notice while we work:

  • Change in normal traffic flow and lane and road closures on Higgins Rd, Wood, Hobart and London Sts (please refer to map below).
  • Driveway access will be impacted at some locations along the alignment. We’ll notify affected properties in advance.
  • Reduced speed limits will be in place.
  • More trucks on the streets around you.
  • Fewer car parks on some streets.
  • Periods of noise when heavy machinery is in operation, including reversing beepers, pumps, and road sawing.
  • Generators and water pumps will be in operation intermittently, including outside of construction hours.
  • Our traffic management team will be around to make sure people, bikes and cars can move around safely.

Want to know more? Watch our video 'What you might hear and see' below.

Don't miss these details

We’re working with ZJW to help us.

During the works ZJW will have a site compound on Higgins Road. This location has been approved by council. The compound will be secure and adhere to strict safety requirements.

Vehicle access to some properties will be impacted for up to 8 - 12 weeks. ZJW will be in contact with affected residents and business owners prior to works.

When we’ve finished the job, we’ll leave things how we found them and make sure we return any areas we’ve impacted as close as possible to their original condition.

Where we will be working

Blue legend icon   Project Alignment and Traffic Impacts (lane closures, reduced speed limits)

What you might hear and see

Frequently Asked Questions

South East Water manages a proactive infrastructure program which involves replacing, maintaining and upgrading the existing water and sewerage infrastructure above and below the ground, so you can always rely on us when you need a drink, a bath, to wash the clothes or dishes and every time you flush or send water down the drain.

We need to upgrade the ageing Elster Creek sewer on Higgins Road, Wood Street, Hobart Street and London Street, Bentleigh to increase the capacity of the sewer network to cater for population growth in the area and future proof the sewerage system.

The population in Melbourne’s south-eastern suburbs is growing, placing pressure on the current sewerage system. These works will upgrade the capacity of the existing Elster Creek sewer, so that future growth can be met.

 The works will: 
• Improve service reliability into the future.
• Future proof the sewer network.
• Reduce ongoing maintenance and repair costs. 

Site investigative works were completed earlier in 2022 to inform the design of the sewer upgrade. Construction started in late 2022 at the Higgins Road Stage and progressed along to the Wood Street and London Street Stages (refer to map above). We're now expecting to finish in early 2024.

We will be installing relief sewer pipes and new concrete manholes along Higgins Road, Wood Street, Hobart Street and London Street, Bentleigh. The installation of relief pipes will be done through a process called underground micro tunnelling. This involves excavating up to four access shafts in stages along each of the streets listed above.

We will renew the sewer pipeline in sections of approximately 100 metres at a time. The works zones will involve some road closures and include temporary fencing and water barriers to ensure the safety of nearby residents and the local community. 

Construction hours will be Monday to Friday between 7am and 6pm. If Saturday works are necessary, they will take place between 8am and 5pm. On the odd occasion, we might need to work at other times for safety, technical or permit reasons.

Construction started in mid October 2022 and we expected to take approximately ten months to complete the project, including reinstatement of road surfaces. We encountered unexpected delayed and now expect to finish in early 2024.

The project will be completed in stages starting on Higgins Road moving to Wood Street and then Hobart and London Streets. We'll keep affected residents updated.

South East Water and their appointed contractor ZJW (Zinfra, Jaydo, WSP Joint Venture) will keep you informed about the project and construction in your area. We'll also keep this webpage up to date.

Sections of the road along the works alignment will be closed for up to six to eight weeks at a time. Vehicle access to driveways in these sections of the road will be blocked. Pedestrian access to properties however will be maintained. The project team will notify affected properties in advance and advise of alternative parking arrangements. The crew will also be available to assist residents where possible. We’re sorry for the inconvenience and will work to make sure this is for as short a time as possible. 

During the works ZJW will have a site compound on Higgins Road opposite the Bentleigh McKinnon Youth Centre. This location has been approved by council. The compound will be secure and adhere to strict safety requirements. 

The construction methods chosen are not likely to cause high levels of dust and vibration. The project team will carry out regular site area inspections during high volumes of work to monitor for the safety and comfort of local residents and the community.  There will be periods of noise from machinery and drilling rigs. The crew will try to keep noisier works to a minimum between 7 am and 9 am. 

If you require property access due to a medical condition, please contact the ZJW Project Manager Dan Schaede immediately on 0423 534 377 or dschaede@jaydo.com.au

No. If you experience any disruption to your water or sewerage services please call our 24/7 Faults and Emergencies team on 13 28 12.

There is no cost to the property owner for these works. 

When we’ve finished the job, we’ll leave things how we found them and make sure we return any areas we’ve impacted as close as possible to their original condition.

Documents

Need to get in touch?

We're here to help.

Elster Creek Sewer Upgrade 

Contact us via phone

1800 728 256 

Contact us via email

engagement@sew.com.au 

Contact us via post

Elster Creek Sewer Upgrade
PO Box 2268
Seaford VIC 3198

Translator Interpreter Service
All languages 03 9280 0779

 

National Relay Service (NRS)
TTY: 13 36 77 (ask for 131 851)