What we’re doing

This project will design and construct a new sewer pump station and upgraded sewer pipeline to help manage sewer flows in the area.  

When it's happening

We're planning to mobilise to site in late October and start construction from Wednesday 4 November. We expect works to take approximately 30 months to complete (depending on weather).

You can expect us to work Monday to Friday between 7 am and 6 pm and Saturday 8 am to 1 pm. On the odd occasion, we might need to work at other times for safety, operational or permit reasons.


What might impact you


We’ll do our best to keep impacts to a minimum, however these are the kinds of things you might notice when construction begins:

  • Machinery on site
  • More trucks on the streets around you
  • Noise from machinery, like beepers when trucks reverse
  • Site access points set up for work near Cardinia Road, Pridley Boulevard and Lecky Road
  • Our site compound will be located within the existing South East Water site along Cardinia Road.
Don’t miss these details

We're working with our delivery partner, BFHI (Beca, Fulton Hogan, Interflow Joint Venture).

Where we will be working

Blue legend icon   Site compound location

 

Blue legend icon   New sewer alignment and pump station location

Frequently asked questions

South East Water’s delivery partner, BFHI (Beca, Fulton Hogan, Interflow Joint Venture) will undertake these works on behalf of South East Water.

No. If you experience any disruption to your water or sewerage services please call our 24/7  Faults and Emergencies team on 13 28 12.

When we’ve finished the job, we’ll leave things how we found them and return any areas we’ve impacted as close as possible to their original condition.

There is no cost to the property owner for these works. 

Contact us via phone

1800 961 899

Contact us via email

engagement@sew.com.au 

Contact us via post

Cardinia Road Employment Precinct Sewer Upgrade (CREP)
PO Box 2268
Seaford VIC 3198

Translator Interpreter Service
All languages 03 9280 0779

 

National Relay Service (NRS)
TTY: 13 36 77 (ask for 131 851)

 

Want to know more about our major projects?

Find out more about existing projects within our service region.