Centre Road Water Mains Renewal

Construction update


We’ve now finished replacing the 150 mm water mains and thank the community for their patience during their construction.

One large main still needs replacing which will be completed during a construction blitz over two super weekends in May (weather permitting). Works during these weekends will commence at 7pm Friday and be continuous (day and night) until 6am on Monday.

Super Weekend 1 – 3rd to 6th May 2019.

Super Weekend 2 – 17th to 20th May 2019.

Until the construction blitz weekend, there will be no further night works. Over the next few weeks in the lead up to the above works, you will see us in the area undertaking preparation works between 10am and 3pm Monday to Friday.

Note:there will be no construction on the weekend of the 10th to 13th May 2019.

Please see project notification with a map included for more information on the Super Weekends construction blitz.

Contact us

For more information about this project please contact:

 
Phone: ​1300 578 515
Email: engagement@sew.com.au
Post: ​​Centre Road Water Main Renewal Project
Community Engagement Team
South East Water
PO Box 2268
Seaford VIC 3198