Works in Albert Park from September 2024

Watch our Project Engineer, Sashi, provide an overview of the project as we prepare to start construction.

 

Where we will be working

Information for residents and businesses

 

What we're doing

The project will increase the capacity of the sewer network to cater for population growth in the area and future proof the sewerage system.

We're completing this project in stages and started works on Stage 1 (in Albert Park) in mid September 2024. We don't expect to impact access to the Park or any clubs, but we may need to occupy a few car parks while we work. 

Stage 2a sewer relining works in Cowderoy Street begin in 
November 2024, while works in Stage 2 at Deakin Street will commence in early January 2025 to approximately May 2025.

We are planning to start stages 4, 5 & 6 (Union Street, St Kilda Road and Beatrice Street) from mid 2025 onwards.

We're still undertaking preliminary investigation works to prepare for construction throughout the project area. These works include cultural heritage investigations, soil sampling and service proving activities. Affected residents will be notified when we need to work nearby.

There will be no interruption to your water or sewer services while we work.

When it's happening

Construction of the new sewer started in mid September 2024. We expect the project to take approximately 18 months, depending on the weather. We'll keep you updated and notify the surounding area before works commence.

We're extending our Monday to Friday hours to 7am to 6pm and Saturdays between 9am and 5pm. This is to try and finish works as quick as we can.

We started works on Stage 1 (in Albert Park) in mid September 2024. It should take around 4 months to complete. We'll pack up over Christmas and the New Year break. We'll return on 6 January 2025 and finish this stage by the end of January 2025. 

  • Stage 1 - Albert Park (near Ross Gregory Oval) 
    September 2024 - January 2025
  • Stage 2a - Cowderoy Street
    November 2024
  • Stage 2 - Deakin & Cowderoy Street
    December 2024 - approximately May 2025
  • Stage 3 - Albert Park (near Hockey Drive)
    April 2025 - August 2025
  • Stages 4, 5 & 6 in Union Street, St Kilda Road and Beatrice Street are being planned to start from mid 2025 onwards.

We expect to finish the whole project by mid 2026.

Information for Albert Park users

 

Access and parking

You'll have access to the park throughout the project, however when we're working nearby you may notice:

  • Traffic detours, including some permanent one way roads.
  • We might have to block off some areas and stop traffic to allow for deliveries, machinery and some work zones. Please adhere to signage on site.
  • Less car parks on Hockey Drive and Village Green Drive.

We'll set up an extra car park off Aughtie drive near Paul Wade Field when we start stage 3 (mid 2025) as we'll need to occupy parking spaces in Hockey Drive.

When we've finished the job, we'll leave things how we found them and return any areas we’ve impacted as close as possible to their original condition.

Bike and Footpaths

Works may impact the Western Bike Path and the footpath opposite. You'll notice temporary fencing for safety of pedestrians and cyclists, as heavy vehicles will be moving in the area. You'll see signage along the bike path to alert cyclists to the changed path conditions ahead and traffic management as required.

Sporting clubs

We're working with clubs to minimise impacts as much as we can. We'll speak to Parks Victoria and each club before works start nearby and discuss their schedule.

Special events

We're working with Parks Victoria to minimise impacts during the project. Before special events, we'll pack up our site as best we can and make the area safe.

What you might hear and see

Frequently Asked Questions

We manage an infrastructure program which involves replacing, maintaining and upgrading the existing water and sewerage infrastructure above and below the ground, so you can always rely on us when you need a drink, a bath, to wash the clothes or dishes and every time you flush or send water down the drain.

 

There are more of us living in the Albert Park area now and, with potential storm surges, floods and extreme weather events from climate change, we need to make sure everyone is protected from sewage surges or overflows. Sewage surges or overflows happens when flooded sewerage pipes aren’t large enough and don’t have the pressure, to take sewage and additional storm water run-off to the local treatment plant.

We’ve awarded the contract to Zinfra, Jaydo, WSP Joint Venture (ZJW) 

South East Water and their appointed contractors will keep you informed about the project and construction in your area, and we’ll work with you to discuss your access needs before we start to build.

The new sewer pipes will be laid beneath the road or footpath, depending on the outcomes of geotechnical investigations and the location of utilities.  The pipes will be laid using trenchless technology, where shafts are dug, then bores are sunk, and pipes pushed through behind them. This is the best way to lay pipes in built up areas because it limits the disruption to the local community.

No, but please don't hesitate to call our 24/7  Faults and Emergencies team on 13 28 12 if you experience disruptions at any time.

Construction hours will be Monday to Friday between 7 am and 5 pm. On the odd occasion we may need to work at other times, including night works, for safety or technical reasons. If we do, we’ll make sure we let you know in advance so you can plan accordingly.

We'll endeavour to make sure your driveway isn’t blocked during construction, but if it is, we’ll let you know beforehand, so you have time to organise alternative parking. But don’t worry. We will be around to help you get out of your driveway in an emergency. 

We'll speak with you in the lead up to construction to understand more about your deliveries, waste removal and customer access, and work with you to make sure these are not impacted. If we do need to block your driveway for a short period of time, we’ll work out alternative arrangements with you prior to works commencing.

Prior to construction commencing we’ll be in touch to understand more about your parking arrangements. We do apologise if local parking is impacted but will work to make sure this is for as short a time as possible.

When we’ve finished the job, we’ll leave things how we found them and make sure we return any areas we’ve impacted as close as possible to their original condition.

No. There is no cost to the property or business owner for these works. 

Need to get in touch?

We're here to help.

Albert Park Branch Sewer Upgrade

Contact us via phone

1800 330 129

Contact us via email

Contact us via post

Albert Park Branch Sewer Upgrade
PO Box 2268
Seaford VIC 3198